The Capex Clock · Cloud and big tech · Q3 2026
What CoreWeave pays for property and equipment
CoreWeave paid $9.44 billion for property and equipment in its latest reported quarter, Jul 1, 2026 to Sep 30, 2026: a pace of $1,188 a second. The figure is the line "Purchases of property and equipment, including capitalized internal-use software" on its cash flow statement, as stated in the 10-Q filed with the SEC on Nov 12, 2026, and it is 4.0 times the figure a year earlier. Since Jan 1, 2023 the filings add up to $45.5 billion. It is all cash paid for property and equipment: it is not all spent on SI, and finance leases are not in it.
Paid by CoreWeave for property and equipment since you opened this page
$0
$1,188 a second$71,264 a minute$103M a day
At last quarter's pace. CoreWeave's latest reported quarter, Jul 1, 2026 to Sep 30, 2026 (92 days), filed Nov 12, 2026: $9.44B divided by the seconds in the quarter. A pace from a filing, not a live reading and not a forecast.
What the number is. The cash a company paid for property and equipment, as it reports the line on its own cash flow statement. What it is not. It is not all spent on SI, finance leases are not in it, and fiscal years differ from company to company. It is a record of filings, not a forecast.
By quarter
11 quarters from the filings
A 10-Q states cash flows for the fiscal year to date, so a quarter is this year to date minus the last one. The fourth quarter is the full year in the 10-K minus the first nine months.
| Quarter | Paid in the quarter | How it is made | Filing |
|---|---|---|---|
Q3 2026 Jul 1, 2026 to Sep 30, 2026 | $9.44B | Year to date $23.6B minus $14.1B | |
Q2 2026 Apr 1, 2026 to Jun 30, 2026 | $6.42B | Year to date $14.1B minus $7.70B | |
Q1 2026 Jan 1, 2026 to Mar 31, 2026 | $7.70B | Year to date $7.70B, the first of the fiscal year | |
Q4 2025 Oct 1, 2025 to Dec 31, 2025 | $4.06B | Full year $10.3B minus $6.25B for the first nine months | |
Q3 2025 Jul 1, 2025 to Sep 30, 2025 | $2.39B | Year to date $6.25B minus $3.86B Stated again in the 10-Q filed Nov 12, 2026; first stated as $6.25B year to date. | |
Q2 2025 Apr 1, 2025 to Jun 30, 2025 | $2.45B | Year to date $3.86B minus $1.41B Stated again in the 10-Q filed Aug 12, 2026; first stated as $3.86B year to date. | |
Q1 2025 Jan 1, 2025 to Mar 31, 2025 | $1.41B | Year to date $1.41B, the first of the fiscal year Stated again in the 10-Q filed May 8, 2026; first stated as $1.41B year to date. | |
Q4 2024 Oct 1, 2024 to Dec 31, 2024 | $3.50B | Full year $8.70B minus $5.20B for the first nine months | |
Q3 2024 Jul 1, 2024 to Sep 30, 2024 | $1.22B | Year to date $5.20B minus $3.99B | |
Q2 2024 Apr 1, 2024 to Jun 30, 2024 | $2.25B | Year to date $3.99B minus $1.74B | |
Q1 2024 Jan 1, 2024 to Mar 31, 2024 | $1.74B | Year to date $1.74B, the first of the fiscal year |
The filings state Jan 1, 2023 to Dec 31, 2023 only as a whole: $2.94B (10-K, filed Mar 2, 2026). It is in the total and is not split into quarters.
Fiscal years
The full years, from the 10-K
| Fiscal year | Paid in the year | Filing |
|---|---|---|
Jan 1, 2025 to Dec 31, 2025 | $10.3B | |
Jan 1, 2024 to Dec 31, 2024 | $8.70B | |
Jan 1, 2023 to Dec 31, 2023 | $2.94B |
The line in the filing
Which line of the cash flow statement this is
- SEC filer
- CoreWeave, Inc. (CIK 1769628)
- Reporting element
us-gaap:PaymentsToAcquirePropertyPlantAndEquipment- Name of the element
- Payments to Acquire Property, Plant, and Equipment
- The company's own caption
- "Purchases of property and equipment, including capitalized internal-use software" (the statement in the filing)
- Fiscal year ends
- Dec 31, 2025 was the last one
- The SEC's data
- every value of this element, as JSON
The line sits in the investing section of the cash flow statement. Companies choose the element they report under, so two companies can file the same kind of spending under different elements. The method lists the elements the Clock reads.
Read it right
What this figure is and is not
- It is cash paid for property and equipment in the period, as CoreWeave reports it to the SEC.
- It is not all SI. Offices, factories, warehouses, land and every other kind of property and equipment are in the same line.
- Finance leases are not in it. Equipment and buildings a company leases are reported elsewhere.