Company File · Compute and data centers · 3 desks
What the public record shows about Nebius and SI
The SI desks hold a public record on Nebius at 3 desks. It shows 377 open jobs on its own job board (Nov 12, 2026); 75 MW of compute announced across 1 project; 2 SI data center sites it owns or uses, 125 MW of IT power by Epoch AI's estimate. Each block below repeats one desk's record with its source and its date. A desk with no record for Nebius is left out. This file is a record, not a verdict.
A record, not a verdict. A Company File repeats what public records and the SI desks show about a company, each with its source and date. It does not judge a company, and a block that is missing means that desk holds no record for it, not that nothing exists.
The record
3 desks, one file
Jump to a block. Each one ends with the source it comes from, the day it was read and a link to the desk that keeps it.
- Open jobsSI Jobs · tsio.si
- Compute announcedThe Gigawatt Ledger · siscto.si
- Compute in the groundThe Power Map and Heat Watch · siscto.si
SI Jobs · tsio.si
Open jobs
377 Open jobs
Nov 12, 2026 Read
Nebius listed 377 open jobs on its own public job board when the SI Jobs desk read it. Every job links to the employer's own posting. See every job by role and place.
Source: Nebius job board on Greenhouse, read Nov 12, 2026. Desk: SI Jobs.
The Gigawatt Ledger · siscto.si
Compute announced
75 MW Announced
1 Projects
The Gigawatt Ledger lists 1 compute project that name Nebius as an operator, with 75 MW announced in total. Public evidence puts 75 MW to 90 MW of that in operation. A project with several operators counts in full for each of them.
- Nebius Mäntsälä Mäntsälä, Uusimaa, Finland · Energized · 75 MW announced · operators: Nebius
Source: The Gigawatt Ledger on siscto.si, as of Nov 11, 2026: company announcements checked against public evidence. Desk: The Gigawatt Ledger on siscto.si.
The Power Map and Heat Watch · siscto.si
Compute in the ground
125 MW IT power, Epoch AI estimate
2 Sites
145 MW Planned
The Power Map lists 2 SI data center sites where Nebius is named as an owner or a user. Epoch AI estimates 125 MW of IT power across them today. A site with an owner and a user counts in full for both. Heat Watch reads the land surface temperature at 2 of them.
- Nebius Mantsala Mantsala, Uusimaa, Finland · owner · expanding · 75 MW IT power (Epoch AI, Jun 29, 2026) · Heat Watch
- Microsoft-Nebius New Jersey Vineland, New Jersey, United States · owner · operating · 50 MW IT power (Epoch AI, Jul 12, 2026) · Heat Watch
Source: Epoch AI, AI data centers, CC BY 4.0, retrieved Nov 10, 2026; power figures are Epoch AI's estimates. Heat Watch as of Nov 17, 2026. Desk: The Power Map and Heat Watch on siscto.si.
The SI 100
Number 10 in The SI 100
Nebius is number 10 of 18 in The SI 100, Q4 2026, with a score of 32.4 from 3 of the seven measures. The release was frozen on Nov 19, 2026; the figures in the blocks above can be newer.
<a href="https://tsio.si/companies/nebius/"><img src="https://tsio.si/si-100/badge/nebius.svg" alt="Nebius in The SI 100, Q4 2026" width="300" height="64"></a>The names this file joins
- Job board
- Nebius (https://job-boards.greenhouse.io/nebius)
- Matched as
- the pattern \bNebius\b on the owner, operator, user, vendor, developer and maker fields of the other desks
One company files, hires and builds under many names. The company name table maps them, and it is published in full on the method page. Spotted a wrong match or a missing record? Tell the team on Telegram or X @entersio with the source.