The Capex Clock · Chip makers · Q2 2026
What NVIDIA pays for property and equipment
NVIDIA paid $2.68 billion for property and equipment in its latest reported quarter, Apr 27, 2026 to Jul 26, 2026: a pace of $340 a second. The figure is a line in the investing section of its cash flow statement, as stated in the 10-Q filed with the SEC on Aug 26, 2026, and it is 41% more than a year earlier. Since Jan 1, 2023 the filings add up to $14.8 billion. It is all cash paid for property and equipment: it is not all spent on SI, and finance leases are not in it.
Paid by NVIDIA for property and equipment since you opened this page
$0
$340 a second$20,429 a minute$29.4M a day
At last quarter's pace. NVIDIA's latest reported quarter, Apr 27, 2026 to Jul 26, 2026 (91 days), filed Aug 26, 2026: $2.68B divided by the seconds in the quarter. A pace from a filing, not a live reading and not a forecast.
What the number is. The cash a company paid for property and equipment, as it reports the line on its own cash flow statement. What it is not. It is not all spent on SI, finance leases are not in it, and fiscal years differ from company to company. It is a record of filings, not a forecast.
By quarter
14 quarters from the filings
A 10-Q states cash flows for the fiscal year to date, so a quarter is this year to date minus the last one. The fourth quarter is the full year in the 10-K minus the first nine months.
| Quarter | Paid in the quarter | How it is made | Filing |
|---|---|---|---|
Q2 2026 Apr 27, 2026 to Jul 26, 2026 | $2.68B | Year to date $4.43B minus $1.76B | |
Q1 2026 Jan 26, 2026 to Apr 26, 2026 | $1.76B | Year to date $1.76B, the first of the fiscal year | |
Q4 2025 Oct 27, 2025 to Jan 25, 2026 | $1.28B | Full year $6.04B minus $4.76B for the first nine months | |
Q3 2025 Jul 28, 2025 to Oct 26, 2025 | $1.64B | Year to date $4.76B minus $3.12B | |
Q2 2025 Apr 28, 2025 to Jul 27, 2025 | $1.90B | Year to date $3.12B minus $1.23B | |
Q1 2025 Jan 27, 2025 to Apr 27, 2025 | $1.23B | Year to date $1.23B, the first of the fiscal year | |
Q4 2024 Oct 28, 2024 to Jan 26, 2025 | $1.08B | Full year $3.24B minus $2.16B for the first nine months | |
Q3 2024 Jul 29, 2024 to Oct 27, 2024 | $813M | Year to date $2.16B minus $1.35B | |
Q2 2024 Apr 29, 2024 to Jul 28, 2024 | $977M | Year to date $1.35B minus $369M | |
Q1 2024 Jan 29, 2024 to Apr 28, 2024 | $369M | Year to date $369M, the first of the fiscal year | |
Q4 2023 Oct 30, 2023 to Jan 28, 2024 | $254M | Full year $1.07B minus $815M for the first nine months | |
Q3 2023 Jul 31, 2023 to Oct 29, 2023 | $278M | Year to date $815M minus $537M | |
Q2 2023 May 1, 2023 to Jul 30, 2023 | $289M | Year to date $537M minus $248M | |
Q1 2023 Jan 30, 2023 to Apr 30, 2023 | $248M | Year to date $248M, the first of the fiscal year |
Fiscal years
The full years, from the 10-K
| Fiscal year | Paid in the year | Filing |
|---|---|---|
Jan 27, 2025 to Jan 25, 2026 | $6.04B | |
Jan 29, 2024 to Jan 26, 2025 | $3.24B | |
Jan 30, 2023 to Jan 28, 2024 | $1.07B | |
Jan 31, 2022 to Jan 29, 2023 | $1.83B |
The line in the filing
Which line of the cash flow statement this is
- SEC filer
- NVIDIA CORP (CIK 1045810)
- Reporting element
us-gaap:PaymentsToAcquireProductiveAssets- Name of the element
- Payments to Acquire Productive Assets
- Fiscal year ends
- Jan 25, 2026 was the last one
- The SEC's data
- every value of this element, as JSON
The line sits in the investing section of the cash flow statement. Companies choose the element they report under, so two companies can file the same kind of spending under different elements. The method lists the elements the Clock reads.
Read it right
What this figure is and is not
- It is cash paid for property and equipment in the period, as NVIDIA reports it to the SEC.
- It is not all SI. Offices, factories, warehouses, land and every other kind of property and equipment are in the same line.
- Finance leases are not in it. Equipment and buildings a company leases are reported elsewhere.
- Fiscal years differ. Each fiscal quarter is placed in the calendar quarter that holds its middle day.
- No forecast. The clock runs at the pace of the last reported quarter. It says nothing about the next one.